How to calculate reorder point and safety stock, with a worked example

By Sohaib Latif, Lead Supply Chain Technologist. . 6 min read.

The short answer: Reorder point = (average daily demand × lead time in days) + safety stock. Safety stock = Z × standard deviation of daily demand × √lead time.

The reorder point formula

The reorder point is the stock level at which you place the next purchase order. Order later and you run out before the delivery lands. Order earlier and cash sits on the shelf.

Reorder point = (average daily demand × lead time in days) + safety stock.

The first part covers what you expect to sell while you wait for the supplier. Safety stock covers the days when demand runs higher than expected or the delivery arrives late.

The safety stock formula

The most widely used statistical formula sizes safety stock from how much your demand varies:

Safety stock = Z × standard deviation of daily demand × √(lead time in days).

Z is the service-level factor. It answers the question: in what share of replenishment cycles are you willing to accept no stock-out?

  • 90% service level: Z = 1.28
  • 95% service level: Z = 1.65
  • 98% service level: Z = 2.05
  • 99% service level: Z = 2.33

Moving from 95% to 99% raises safety stock by about 41%. That is why a single service level for every SKU is expensive: fast, critical items deserve 98–99%, slow ones rarely do.

A worked example

A distributor sells an average of 40 units a day of one SKU. The standard deviation of daily demand is 12 units, the supplier lead time is 9 days, and the target service level is 95%.

  • Safety stock = 1.65 × 12 × √9 = 1.65 × 12 × 3 = 59.4, rounded up to 60 units
  • Demand during lead time = 40 × 9 = 360 units
  • Reorder point = 360 + 60 = 420 units

When stock on hand plus stock on order falls to 420 units, raise the purchase order.

Compare that with the common rule of thumb, (maximum daily demand × maximum lead time) − (average daily demand × average lead time). With a peak of 55 units a day and a worst-case lead time of 12 days, it gives 660 − 360 = 300 units of safety stock: five times more cash tied up to protect the same SKU.

Four mistakes that cause stock-outs anyway

  • Setting it once. Demand and lead times drift, so a reorder point calculated last year is wrong today. Recalculate at least monthly.
  • Using the quoted lead time. Use what suppliers actually deliver, measured from purchase order date to goods receipt.
  • Ignoring lead time variability. If deliveries swing by a week, add that variation to the calculation or the formula will understate the risk.
  • Counting only stock on hand. Compare the reorder point with stock on hand plus open purchase orders, minus backorders.

When a spreadsheet stops being enough

The formula is simple. Keeping it current for 2,000 SKUs across several warehouses is not, and that is where most teams fall behind.

An inventory agent recalculates reorder points and safety stock for every SKU from live ERP data, then sends planners only the exceptions: items about to breach, and items carrying far more cover than they need.